Please find attached the September 2022 Council maintenance and minor works programme.
The recent wet weather is affecting timing of works as crews work to clear slips and repair roads. For the latest information please check out the weekly roadworks report on the WCC website.
Roads – Road works and road closures – Wellington City Council
Thank you for sharing this information with your respective community groups/organisations. If we need to update an email address, please let me know.
Note that the information in the document does not include work for other organisations working in the road corridor such as Waka Kotahi, Wellington Water, Wellington Electricity or building works which require access to the road or footpath.
If you would like more information or have any questions feel free to contact us on (04) 499 4444.
Ngā mihi
Denise Beazley Network Activity Manager | | Wellington City Council M 021 597 166 E Denise.Beazley@wcc.govt.nz |
The main ones to note in the Bay are:
Derwent Street, Island Bay | Road Dig Outs | September 6-7 | Stop/Go | 7am-5pm. Section between Moselle and Humber |
Severn Street, Island Bay | Kerb, channel and footpath renewal | August 15 – November | Stop/Go | 7am-5pm Section between Frobisher Street intersection and Owhiro Bay Road |
Derwent Street/Esplanade intersection, Island Bay | Pavement repairs, Kerb, channel and footpath renewals | September 12 – October 21 | Stop/Go | 7am-5pm, 9am-4pm in intersection |
Severn Street, Island Bay | Kerb, channel and footpath renewals | late September – December | Stop/Go | 7am-5pm Section between Southern Cross Cres and Moselle St |